Back to top
Reported by NEXANS on 8 January 2019

Nexans completes high voltage cable project to connect Kype Muir wind farm to Scotland’s power grid

The Scottish Government has set an ambitious target for renewable energy resources to meet 100 percent of the country’s gross annual electricity consumption by 2020. Large onshore wind farms will play a key role in meeting this target, such as the 88 megawatt (MW) Kype Muir wind farm, where Nexans has just completed a project to provide a 16 km 132 kilovolt (kV) underground grid connection for SP Energy Networks.

(Courtesy of pexels.com)

With a total capacity of over 10 gigawatt (GW), Scotland’s renewable electricity generation sector is now over three times bigger than it was at the end of 2008. Onshore wind is the biggest single renewable technology, accounting for over 74 per cent of installed capacity. The Kype Muir wind farm comprises 26 turbines and is a flagship development for the Banks Group. It is located around 5 km from the town of Strathaven in South Lanarkshire.

A key element in the wind farm project is the 16 km underground cable connection required to link the new 132 / 33 kV SP Energy Networks substation at the Kype Muir site with the existing Coalburn 400 / 132 kV grid substation. SP Energy Networks awarded the contract for this connection to Nexans France based on its proven capability to meet a challenging project timescale of just eight months while providing project delivery of services including design, manufacture, and delivery of the cable, civil works (excluding duct installation), cable laying, design and supply of the cable accessories, jointing and commissioning.

To provide the three individual phases for the grid connection, Nexans has supplied a total of around 50 km of cross-linked polyethylene (XLPE) insulated cable with an aluminium conductor and an aluminium welded sheath, manufactured at Nexans Benelux factory in Charleroi, Belgium. The accessories, manufactured at Nexans Switzerland’s plant in Cortaillod, include six FEV outdoor terminations and 60 cross-bonding joints with associated link boxes.

"The Kype Muir to Coalburn 132 kV undergound cable was a challenging project but good working relationships between SP Energy Networks and Nexans project teams led to a positive outcome. Nexans’ commitment to meet a challenging programme was recognised by all involved in the project.” - David Raftery; Project Unit Manager, Integrated & Circuits Programmes, SP Energy Networks

“The success of the Kype Muir project further demonstrates Nexans’ expertise in project delivery for wind farm projects with a demanding schedule and environment. We are also delighted to have further enhanced our working relationship with SP Energy Networks from our UK office in Edinburgh, after the successful execution of a similar wind farm project at Kilgallioch and other recent substation projects at Wishaw, Windyhill and Maentwrog.” - Mike Rintoul; Head of Project Delivery at Nexans

References

[1]

Nexans, société anonyme. Press release - Nexans completes high voltage cable project to connect Kype Muir wind farm to Scotland’s power grid. URL: https://www.nexans.com/newsroom/news/details/2019/01/Nexans-completes-high-volta.... [Date Accessed: 08/01/2019].

Project Development & Execution

21 Jan | MHI Vestas Achieves Final Turbine Installation at Horns Reef 3

MHI Vestas Offshore Wind has installed the final turbine at Horns Reef 3 offshore wind park, now featuring the most powerful turbines in Denmark

Project Development & Execution

17 Jan | ACCIONA completely renovated wind farm service Spain

  • El Cabrito, located at Tarifa (Cadiz), goes from ninety 330-kW wind turbines installed in 1995 to twelve 3-MW and 1.5-MW machines of Nordex technology
  • The installation will produce 16% more clean energy with the same capacity (30 MW) as the obsolete wind farm
  • The renewal has reduced its environmental impact, as well as its visual and noise profile, and makes it easier for birdlife to fly through.

Project Development & Execution

15 Jan | ABO Wind installs 30 megawatts of wind power in Tunisia

  • Project developer obtains permission and remuneration in tender process
  • The wind farm located 35 kilometres south-east of Tunis to be commissioned in 2021

Project Development & Execution

15 Jan | ERG launches two new wind farms in France totalling 31 MW - Installed power in the country exceeds 300 MW

ERG is pleased to announce the completion of the commissioning phase for Parc Eolien de la Vallée de Torfou (17.6 MW - estimated average annual output 47 GWh), a wind farm forming part of the 768 MW of assets under construction and being developed by Epuron, acquired last year (see Press Release dat

Transmission

19 Nov | Nexans wins major power export cable contract for Ørsted’s Hornsea 2 wind farm

Nexans has won a contract worth over 150 million euros to help Ørsted deliver the most affordable electricity from offshore wind yet. The project covers the supply of over 200 km of the 245 kV high voltage alternating current (HVAC) subsea export cable system for the near shore section of Hornsea 2 wind farm.

Business & Finance

07 Nov | Nexans is awarded a multimillion-euro contract for Ørsted’s Borssele 1 and 2 wind farms off the Netherlands coast

Major contract for 66 kV submarine inter-array cable with associated accessories is the first to be placed under a new five-year framework agreement recently signed by Nexans and Ørsted.

Transmission

16 Oct | Nexans wins export cable contract for Belgium's Northwester 2 offshore wind farm

Nexans will supply a subsea power cable and associated accessories for the Northwester 2 offshore wind farm that will provide enough electricity to power around 220,000 Belgian homes.

Transmission

08 Oct | Nexans Wins Multimillion Euro Contract at UK’s Triton Knoll Offshore Wind Farm

  • J Murphy & Sons Limited awarded Nexans with a contract worth over €35 million, to supply the land export cable for the Triton Knoll offshore wind farm.
  • Nexans will supply cross-linked polyethylene (XLPE) insulated alternating current (AC) cables required to connect the offshore wind farm to the UK grid.
  • With a capacity of approximately 860 MW, the Triton Knoll wind farm will have the capability to supply the equivalent of over 800,000 UK households per year with renewable electricity.