Invenergy Announces Start of Commercial Operations of Upstream Wind Energy Center

Tymien (Courtesy of Invenergy LLC)

Invenergy, a leading privately-held global developer and operator of sustainable energy solutions, announced today the completion of construction and the start of commercial operations of the 200-megawatt Upstream Wind Energy Center in Antelope County, Nebraska.

Located just north of the City of Neligh, Upstream was developed and constructed by Invenergy and will generate enough electricity to power 68,000 American homes.

The project supported 275 workers during peak construction and will create 11 permanent full-time operations and maintenance jobs for the long-term operation of the project. Upstream will contribute approximately $2 million annually to the local economy through tax payments, lease payments to participating landowners, and wages and benefits for employees.

Invenergy and WEC Energy Group signed a Purchase and Sale Agreement for WEC Energy Group’s acquisition of an 80 percent interest in the project. Invenergy will retain a 20 percent interest and provide operations and maintenance, asset management and energy management services for the project.

“We are proud to grow our investment in Nebraska and to continue our track record of project execution and strong community relationships,” said Mick Baird, Senior Vice President, Renewable Development for Invenergy. “WEC is an ideal partner for Invenergy given their commitment to renewable energy.”

“We commend Invenergy for achieving commercial operation and are pleased to partner with them in the deployment of this valuable renewable energy resource,” said Dan Krueger, Executive Vice President, WEC Infrastructure.

This is the fourth project Invenergy has successfully developed and built in Nebraska.

References

[1]

Invenergy LLC. Press release - Invenergy Announces Start of Commercial Operations of Upstream Wind Energy Center. URL: https://invenergyllc.com/news/invenergy-announces-start-of-commercial-operations.... [Date Accessed: 17/01/2019].

[2]

Invenergy LLC. Media Center > Photos & Videos. https://invenergyllc.com/news/media-resources. [Date Accessed: 13/02/2018].

Project Development & Execution

21 Jan | MHI Vestas Achieves Final Turbine Installation at Horns Reef 3

MHI Vestas Offshore Wind has installed the final turbine at Horns Reef 3 offshore wind park, now featuring the most powerful turbines in Denmark

Project Development & Execution

17 Jan | ACCIONA completely renovated wind farm service Spain

  • El Cabrito, located at Tarifa (Cadiz), goes from ninety 330-kW wind turbines installed in 1995 to twelve 3-MW and 1.5-MW machines of Nordex technology
  • The installation will produce 16% more clean energy with the same capacity (30 MW) as the obsolete wind farm
  • The renewal has reduced its environmental impact, as well as its visual and noise profile, and makes it easier for birdlife to fly through.

Project Development & Execution

15 Jan | ABO Wind installs 30 megawatts of wind power in Tunisia

  • Project developer obtains permission and remuneration in tender process
  • The wind farm located 35 kilometres south-east of Tunis to be commissioned in 2021

Project Development & Execution

15 Jan | ERG launches two new wind farms in France totalling 31 MW - Installed power in the country exceeds 300 MW

ERG is pleased to announce the completion of the commissioning phase for Parc Eolien de la Vallée de Torfou (17.6 MW - estimated average annual output 47 GWh), a wind farm forming part of the 768 MW of assets under construction and being developed by Epuron, acquired last year (see Press Release dat

24 Jul | Invenergy Announces Start of Commercial Operations of Santa Rita East Wind Farm

Invenergy completes construction of Texas wind farm that is supporting sustainability goals of Grupo Bimbo, Merck and Novartis.

08 Mar | DTE Energy and Invenergy Announce Commercial Operations of Michigan’s Largest Wind Project

CHICAGO (March 8, 2019) – DTE Energy and Invenergy today announced the start of commercial operations at the Pine River wind project in Gratiot and Isabella Counties in central Michigan.

06 Mar | Invenergy Services Honored with American Wind Energy Association’s (AWEA) 2019 Excellence in Operations Award

Award represents third AWEA Excellence in Operations recognition for O&M industry leader Invenergy Services

Chris Meehan, VP, Wind Operations, Invenergy Services, accepts award at AWEA’s O&M and

Safety Conference in San Diego

Business & Finance

08 Jan | Invenergy Completes Construction Financing for 300-Megawatt Santa Rita East Wind Farm

Invenergy, a leading privately-held global developer and operator of sustainable energy solutions, announced that it completed construction financing on December 19, 2018 for its 302.4-megawatt Santa Rita East Wind Farm, located approximately 70 miles west of San Angelo, Texas.