Reported by Ideol on 19 September 2018

Ideol's first demonstrator is delivering power to the grid

The connection of the electricity export cable and a final series of tests carried out in recent days enabled the Floatgen wind turbine, which is installed 22 km off Le Croisic (Loire-Atlantique), to become fully operational on Tuesday 18 September.

(Courtesy of Ideol SA)

This announcement is a highly symbolic step for Ideol, because this wind turbine is the first operational unit of the floating foundation concept patented by the company. A second unit of the Ideol foundation will soon be operational off Japan.

References

[1]

Ideol SA. Press release - Ideol's first demonstrator is delivering power to the grid. URL: https://www.ideol-offshore.com/en/ideols-first-demonstrator-delivering-power-gri.... [Date Accessed: 01/10/2018].

Project Development & Execution

21 Jan | MHI Vestas Achieves Final Turbine Installation at Horns Reef 3

MHI Vestas Offshore Wind has installed the final turbine at Horns Reef 3 offshore wind park, now featuring the most powerful turbines in Denmark

Project Development & Execution

11 Jan | PKN ORLEN a step closer to building an off-shore wind farm in the Baltic Sea

An ORLEN Group company Baltic Power is about to commence surveys to assess the environmental impacts and wind conditions within its off-shore wind farm licence area in the Baltic Sea. To that end, an agreement was signed with a consortium comprising MEWO S.A. and the Maritime Institute of Gdańsk, with a view to obtaining an environmental permit for the project and determining the production potential of the planned off-shore wind farm.

Project Development & Execution

27 Dec | The first turbine is spinning at Horns Rev 3 offshore wind farm

When the Danes switched on their ovens to prepare their meals during the Christmas holidays, it was partly powered by the first electricity from Denmark's next new offshore wind farm - Horns Rev 3.

Project Development & Execution

13 Dec | Tideway completes installation of longest AC offshore wind export cable at Hornsea One in the UK

A world first and a major construction milestone was reached at Ørsted’s Hornsea Project One offshore wind farm in the UK when Tideway completed the export cable installation.

Business & Finance

22 Oct | The EU rewards Ideol with €2.5 million to finance the industrialization and commercial development of its technology

Ideol has just received a €2.5 million grant from the European Commission under the Horizon 2020 - SME Instrument programme. This funding is outstanding since this very selective programme only rewards 5% of the candidate projects.

Transmission

22 May | Ideol and STX team up to develop the next generation of offshore substations

Ideol and STX Europe Offshore Energy, the well-known EPCIM supplier of substations to the bottom-fixed offshore wind industry, announce the development of a breakthrough floating substation. This one will be compatible with both bottom-fixed and floating offshore wind farms.

15 May | Floatgen is installed

The floating offshore wind turbine Floatgen was tugged to its permanent offshore installation site – the SEM-REV test site – during the night of April 30th.

26 Apr | Ideol to team up with Acacia Renewables to develop Japan’s first commercial-scale floating wind farm

French floating offshore wind leader Ideol and Acacia Renewables, a wholly owned Japanese renewable energy development platform of Macquarie Capital, signed a Memorandum of Understanding (MOU) in March aiming at developing Japan’s first utility scale commercial floating offshore wind farm.